Construction at ul. Kilińskiego to be completed in May 2016

Construction works at ul. Kilińskiego are to be completed by May this year. Following several delays, the board of Raods and Transport in Łódź confirmed the final completion date.

construction-kilinskiego-lodz

Reconstruction of Kilińskiego in Łódź began in June last year. Initially, the modernization was planned to take three months and was to be completed in September. First, however, the date was postponed to the end of November, and now to the 15th of May. The board of Roads and Transport is currently in discussion with the contractor. Potentially they may face a fine for the delays.

Image: Radio Lodz